Sr No Scheduled Employment Area Category of workers
Un-Skilled Semi-Skilled/Unskilled Supervisory Skilled/Clerical Highly Skilled
Basic Min Wage V.D.A. Total Min Wage Basic Min Wage V.D.A. Total Min Wage Basic Min Wage V.D.A. Total Min Wage Basic Min Wage V.D.A. Total Min Wage
( In Rupees Per Day ) ( In Rupees Per Day ) ( In Rupees Per Day ) ( In Rupees Per Day )
1 Agriculture A 114 112 226 125 122 247 137 132 269 153 145 298
B 104 102 206 116 112 228 125 122 247 141 135 276
C 102 102 204 107 102 209 115 112 227 125 122 247
2 Industrial Worker (employees employed in loading and unloading in 1)goods sheda, parcel offices of railways; 2) other goodssheds, godowns, warehouses; 3) docks and ports A 180 168 348 80 115 89 204 125 97 222
B 150 140 290 0
C 120 113 233 0
3 Industrial Workers employed in Gypsum Mines, Barytes Mines, Mauxite Mines, Manganese Mines, China Clay Mines, Kyanite Mines, Copper Mines, Clay Mines, Magnesite Mines, White Clay Mines, Stone Mines, Steatite Mines, Ochre Mines, Asbestos Mines, Fire Clay Mines, Chromite Mines, Quartzite Mines, Quartz Mines, Silica Mines, Graphite Mines, Felspar Mines, Laterite Mines, Dolomite Mines, Red Oxide Mines, Wolfram Mines, Iron Ore Mines, Granite Mines, Rock Phosphate Mines, Hematite Mines, Marble and Calcite Mines, Uranium Mines, Mica Mines, Lignite Mines, Gravel Mines, Slate Mines, Magnetite Mine For work above ground 120 113 233 150 140 290 180 168 348 210 195 405
For work below ground 150 140 290 180 168 348 210 195 405 240 221 461
4 Sweeping and Cleaning A 180 168 348
B 150 140 290
C 120 113 233
5 Watch and Ward (without arms) A 200 185 385
B 170 158 328
C 140 132 272
6 Watch and Ward (with arms) A 220 204 424
B 200 185 385
C 170 158 328
7 Construction or maintenance of roads or runways in buliding operations including laying down underground electric,wireless, radio, television, telephone, telegraph and overseas communication cables and similar other underground cabling work, electric lines, water supply lines and sewerage pipe lines A 180 168 348 200 185 385 220 204 424 240 221 461
B 150 140 290 170 158 328 200 185 385 220 204 424
C 120 113 233 140 132 272 170 158 328 200 185 385
8 Workers engaged in Stone Mines for Stone Breaking and Stone Crushing Category Daily Basic Wage Daily VDA Total Daily Minimum Wages
1. Excavation & removal of over burden with 50 m lead/1.5 meters lift
(a) Soft Soil 103.53 129 232.53
(b) Soft Soil with Rock 157.78 194 351.78
(c ) Rock 208.09 258 466.09
2.  Removal and Staking of rejected stones with 50 meters lead 1.5 meters lift 82.44 104 186.44
Stone Breaking or Stone Crushing for the stone size Daily Basic Wage Daily VDA Total Daily Minimum Wages
(a) 1.0 inch to 1.5 inches 646.44 799 1445.44
(b) Above 1.5 inches to 3.0 inches 552.12 684 1236.12
(c ) Above 3.0 inches to 5.0 inches 322.69 400 722.69
(d) Above 5.0 inches 264.47 329 593.47